Identifying the Risk Impact on Cost and Time of the Egyptian Non-Residential Buildings Projects

Authors

  • Medhat M. A. Osman  Department of Architectural Engineering, Faculty of Engineering, Minia University, Minia, Egypt
  • Usama H. Issa  Department of Civil Engineering, Faculty of Engineering, Minia University, Minia, Egypt and Department of Civil Engineering, College of Engineering, Taif University, Taif, Saudi Arabia
  • Ayman M. Zakaria Eraqi  Department of Architecture, Faculty of Fine Arts, Minia University, Minia, Egypt

DOI:

https://doi.org//10.32628/IJSRSET196659

Keywords:

Risk analysis, Non-Residential Buildings, Cost Overruns, Time Delays, Egypt.

Abstract

Construction projects in Egypt were typically influenced by multiple risk factors which have various impacts on both cost and time objectives that lead to project cost overruns and time delays. This paper presents the results of an investigation study concerns with the identification and assessment of risks associated with the Egyptian Non-Residential Buildings Projects (ENRBP). The study explores risk factors probability of occurrence and their effects on cost and time of these projects. A field survey was conducted with professionals in the construction projects in EGYPT for a purpose of collecting the required data of the risk factors characteristics. Based on results analysis, several risk factors were identified and categorized into fifteen risk groups as well as they were prioritized based on their effects on cost and time. A high agreement for ranking risk factors among contractors, consultants and owners was acquired. The list of the major risks included many factors such as: dramatic changes in the materials prices and Adopting direct attribution system rather than tendering and bidding systems. The most expected average increase of the cost overruns and time delays was more than 20% of the project planned budget and schedule. Finally, the analysis and findings showed that risk factors were very close in their impacts on both cost and time of ENRBP.

References

  1. Jeong, YS., Jung, HK., Jang, HK., Yu, KH. (2014) A Study on the Reference Building based on the Building Design Trends for Non-residential Buildings. Journal of the Korean Solar Energy Society 34(3), 1-11.
  2. Rezaie, B., Dincer, I., Esmailzadeh, E. (2014) Evaluation of Sustainable Energy Options for Non-residential Buildings. Progress in Sustainable Energy Technologies II.
  3. Panopoulos, K., Papadopoulos, A. M. (2017) Smart facades for non-residential buildings: an assessment. Advances in Building Energy Research 11(1).
  4. Bode, G., Behrendt, S., Futterer, J., Muller, D. (September 2017) Identification and utilization of flexibility in non-residential buildings. Energy Procedia 122, 997-1002.
  5. Trachte, S., Salvesen, F. (2014) Sustainable Renovation of Non Residential Buildings, a Response to Lowering the Environmental Impact of the Building Sector in Europe. Energy Procedia 48, 1512-1518.
  6. Droutsa, K. G., Kontoyiannidis, S., Dascalaki, E. G., Balaras, C. A. (2017) Benchmarking Energy Use of Existing Hellenic Non-Residential Buildings. Procedia Environmental Sciences 38, 713-720.
  7. Kierdorf, D., Botzler, S., Meier-Dotzler, S. (2016) ASSESSING SUSTAINABLE RETROFITS OF PUBLIC NON-RESIDENTIAL BUILDINGS. In : BEHAVE 2016 4th European Conference on Behaviour and Energy Efficiency, Combira.
  8. Solla, M., Ismail, L. H., Yunus, R. (February 2015) Evaluation of Non-Residential Green Building in Malaysia. In : Internationa Conference Data Mining, Civil and Mechanical Engineering, Bali.
  9. Gray, C. F., Larson, E. W. (2003) Project management: the managerial process, 2nd edn. MrGraw-Hill.
  10. Kerzner, H. (2006) Project management: a systems approach to planning, scheduling, and controlling 9th edn. John Wiley&Sons, Inc..
  11. Baker, C., Zeng, J. (2005) 12A fuzzy-logic-based approach to qualitative risk modelling in the construction process., 1-12.
  12. Chapman, CB., Ward, SV. (1997) Project risk management: processes, techniques and insights. John Wiley & Sons Ltd, Chichester.
  13. Tummala, V. MR., Burchett, J. F. Applying a Risk Management Process (RMP) to manage cost risk for an EHV transmission line project. International Journal of Project Management 17(4), 223-235.
  14. Ofori, G. (1993) Research on construction industry development at the crossroads. Construction Management and Economics 11, 175-185.
  15. Khodeir, L. M., El Ghandour, A. (2019) Examining the role of value management in controlling cost overrun [application on residential construction projects in Egypt]. Ain Shams Engineering Journal 10(3), 471-479.
  16. Khodeir, L. M., Nabawy, M. (2019) Identifying key risks in infrastructure projects – Case study of Cairo Festival City project in Egypt. Ain Shams Engineering Journal 10(3), 613-621.
  17. Issa, U. H., Ahmed, A. (2014) On the quality of driven piles construction based on risk analysis. International journal of civil engineering 12(2), 88-96.
  18. Marzouk, M. M., El-Rasas, T. I. (2014) Analyzing delay causes in Egyptian construction projects. Journal of advanced Research 5(1), 49-55.
  19. Sharaf, M. MM., Abdelwahab, H. T. (2015) Analysis of Risk Factors for Highway Construction Projects in Egypt. Journal of Civil Engineering and Architecture 9, 526-533.
  20. Issa, U. H. (2012) Developing an Assessment Model for Factors Affecting the Quality in the Construction Industry. Journal of Civil Engineering and Architecture 6(3), 364-371.
  21. Issa, U. H. (2012) A model for time overrun quantification in construction of industrial projects based on risk evaluation. Journal of American Science 8(8), 523-529.
  22. Shen, L. Y., George, W. C., Catherine, S. K. (2001) Risk assessment for construction joint ventures in china. 25) Shen, L. Y., George W. C. & Catherine Journal of Construction Engineering and Management 127(1), 76-81.
  23. Thomas, A. V., Kalidindi, S. N., Ananthanarayanan, K. (2003) 27) Thomas, A. V., Kalidindi, S. N. Risk perception analysis of BOT road project participants in India. 27) Thomas, A. V., Kalidindi, S. N. & Ananthanarayanan, K. (2003). Risk perceptio Journal of Construction Management and Economics 21(4), 393-407.
  24. Issa, U. H., Ahmed, A., Ugai, K. (2014) A Decision support system for ground improvement projects using gypsum waste case study: embankments construction in Japan. Journal of Civil and Environmental Research 4(1), 74-84.
  25. Long, N. D., Ogunlana, S., Quang, T., Lam, K. C. (2004) Large construction projects in developing countries: a case study from Vietnam. International Journal of Project Management 22(7), 553-561.
  26. Altman, D. G. (1991) Practical statistics for medical research. Chapman & Hall, London.
  27. Finkelstein, M. O., Levin, B. (2000) Statistics for social science and public policy. Springer.

Downloads

Published

2020-01-30

Issue

Section

Research Articles

How to Cite

[1]
Medhat M. A. Osman, Usama H. Issa, Ayman M. Zakaria Eraqi, " Identifying the Risk Impact on Cost and Time of the Egyptian Non-Residential Buildings Projects, International Journal of Scientific Research in Science, Engineering and Technology(IJSRSET), Print ISSN : 2395-1990, Online ISSN : 2394-4099, Volume 7, Issue 1, pp.01-12, January-February-2020. Available at doi : https://doi.org/10.32628/IJSRSET196659