Developing Appropriate Labour Constants for Building Construction Processes in Nigeria

Authors

  • Ngwu Chukwuemeka  Department of Surveying Quantity, Nnamdi Azikiwe University, Awka
  • Okolie  Department of Building, Nnamdi Azikiwe University Awka
  • K. C.  
  • Ogunoh P. E.  

Keywords:

Standard time, standard output, labour, unit rates, work study, estimators

Abstract

Labour is one of the key components of unit rates for bill of quantities items. One of the major challenges facing estimators when pricing bills of quantities for tendering is their inability to quickly lay hands on proper information about labour thereby resulting in high variability of tender prices among contractors bidding for building contracts in Nigeria. These information are the standards, usually given as constants in the form of time necessary for the manual completion of a defined quantity of work (standard time (st), or in the form of unit output, standard output (sop) for a specified working time). The aim of this study was to improve the reliability of tendering among contractors and assist in effective project planning and control. Consequently, a survey was carried out in ten organized building sites in the south east states of Nigeria with a view to evolving appropriate labour constants for building processes (concrete work and block work). The sites were selected using purposive/judgmental sampling technique. Work study was used to evolve appropriate labour constants and this involved a full scale time study for each of the operations that make up the activity for a process. This was done by observing and recording the operations using stopwatches; the start and finish durations of each operation per shift for different cycles as well as measuring the quantity of work carried out by each gang for eight-hour working day. A three-time estimate using the formula for most probable time to complete each operation that makes up an activity relative to the quantity of work performed. Students t-statistic and mean score index were used for the analysis. The tradesmen were also required to estimate their outputs in selected tasks. The evolved labour constants were more realistic and appropriate for pricing than the claimed outputs by the tradesmen and, therefore recommended as veritable tools for realistic pricing. This will reduce the level of variability in tender sum among contending contractors. It will further assist in effective project planning and control through realistic determination of optimal labour force in the execution of building projects.

References

 


[1] Adeyemi, A. Y., Alli, O. R. (2000). Cost Implications of Alternative Staircase Design in Residential Buildings. Proceedings at the Workshop on Effective Housing in the 21st Century. Akure, Nigeria. p. 15 – 25.

[2] Alarcon, L. F., Calderon, R. (2003), "Implementing Lean Production Strategies in Construction Companies": Proceedings of the 2003 Construction Research Congress, ASCE, Honolulu. 

[3] Chao, L. C., Skibniewski, M. J. (1994), "Estimating Construction Productivity: Neural-Network-Based Approach", Journal of Computing in Civil Engineering, 8(2), 234-251.

[4] Eldin, N. N., Egger, S. (1990), "Productivity Improvement Tool: Camcorders", Journal of Construction Engineering and Management, 116(1), 100-111.

[5] Ezeldin, S. A., Sharara, L. (2006), "Neural Networks for Estimating the Productivity of Concreting Activities", Journal of Construction Engineering and Management, 132(6). 650-656. 

[6] Forsberg, A., Saukkoriipi, L. (2007), "Measurement of Waste and Productivity in Relation to Lean Thinking", in: Pasquire, C. L. and Tzortzopoulos, P. (ed.), Proceedings of 15th Annual Conference of the International Group for Lean Construction, East Lansing, Michigan, 67-77.

[7] Hewage, K. N., Ruwanpura, Y. J. (2009), "A novel solution for construction on-site communication - the information booth", Canadian Journal of Civil Engineering. 36(4). 659-671. 

[8] Iyagba R., Ayandele O. (2005): Analysis of factors Affecting Nigerian Construction Workers’ Productivity. The Quantity Surveyor, Journal of the Nigerian Institute of Quantity Surveyors, 54(3): 2 – 7. 

[9] LeMenager, P. A. (1992), “Technology is Here-Are You Ready?”, Journal of Management in Engineering, 8(3), 261-266. 

[10] Oglesby, C. H., Parker, H. W. and Howell, G. A. (1989), "Productivity Improvement in Construction". McGraw-Hill Book Co., New York.

[11] Okereke P. A (2002). Basic Principles in the Organization of Construction Processes. FUTO Press, Owerri.

[12] Olomolaiye P. O., Ogunlana S. O. (1989): An evaluation of Production outputs in Key Building Trades in Nigeria, Journal of Construction Management and Economics, 7 75 – 86.


Downloads

Published

2015-04-25

Issue

Section

Research Articles

How to Cite

[1]
Ngwu Chukwuemeka, Okolie, K. C., Ogunoh P. E. "Developing Appropriate Labour Constants for Building Construction Processes in Nigeria" International Journal of Scientific Research in Science, Engineering and Technology (IJSRSET), Print ISSN : 2395-1990, Online ISSN : 2394-4099, Volume 1, Issue 2, pp.144-150, March-April-2015.