Change Management in Electrical Instillation Projects

Authors

  • Sneha Yawalekar  Student, Project Management, Department of Production Engineering, VJTI, Mumbai, Maharashtra, India
  • B.E. Narkhede  Associate Professor, Department of Production Engineering, VJTI, Mumbai, Maharashtra, India
  • Rakesh Raut  Assistant Professor, NITIE, Mumbai, Maharashtra, India

Keywords:

Change Order, Electrical Installation, Causes, Effects, Controls and Management

Abstract

Change is very common thing in any project due to various factors like design change or error, extra or altered requirements, work schedule change or any unseen and unpredicted conditions which results in unfavorable conditions of project constraints, time, cost and quality. Change in projects can be considered as a risk and accordingly the mitigation techniques have to be implied to minimize its adverse implications and the process is termed as change control and management. Electrical equipment capacity and design for electricity distribution in a building depends upon civil and other utility design and energy requirement. So changes in design, plan, specification of any other facility results in major change in the electrical installation capacity and design. This study investigates the characteristics of the general electrical installation industry. Also it highlights main causes of change orders and their effects on the project. A questionnaire survey is conducted among the personals directly involved in electrical installations in a construction industry. Overall study finds that changes requested by the owner are the main cause for change order and schedule overrun is the main impact followed by budget overrun. Clearly defined scope for the change orders seems to be the common practice to control and manage the change order.

References

  1. Ibrahim Yitmen, Huseyin Sevay, Cem Taneri And Hakan Yalciner (2006) "An Expert System For Quantifying The Impact Of Change Orders On Project Performance", Joint International Conference on Computing and Decision Making in Civil and Building Engineering, June 14-16, 2006 - Montréal, Canada
  2. Naoum S. (1994), "Critical analysis of time and cost of management and traditional contracts", Journal of Construction Engineering and Management, 120(4), 687-705
  3.  Rashid, I., Elmikawi, M. and Saleh, A. (2012), "The Impact of Change Orders on construction projects Sports Facilities Case Study", Journal of American Science, 8(8), 628-631.
  4. A.H. Al-Dubaisi.(2000) Change Orders in Construction Projects In Saudi Arabia, M.Sc. Thesis, The college of graduate studies, KFUPM. Dhahran, Saudi Arabia, 2000.
  5. Homaid, N., Eldosouky, A. and AlGhmdi, M. (2011), "Change Orders in Saudi Linear Construction Projects", Emirates Journal for Engineering Research, 16(1), 33-42.
  6. Ibrahim Albalushi, Fathoni Usman and Ali S. Alnuaimi(2013), "Construction Cost Overrun and Variations: Investigation on Its Causes and Consequences", Australian Journal of Basic and Applied Sciences, 7(14) December 2013, Pages: 311-323
  7. Diekmann, J. & Nelson, M. (1985) " Construction claims: frequency and severity", Journal of Construction Engineering and Management, March, 111: 74-81.
  8. Fleming A, S. Senaratne, M. Sexton, M. Sun, G. Aouad, "Managing Project Change in Construction:The Dependency Framework"
  9. Keane, P., Sertyesilisik, B. and Ross, A. (2010), "Variations and Change Orders on Construction Projects". Journal of Legal Affairs and Dispute Resolution in Engineering and Construction, 2(2), 89-96.
  10.  Soares, R. (2012), "Change Orders: the Output of Project Disintegration", International Journal of Business, Humanities and Technology, 2(1), 65-69.
  11. Alia Alaryan, Emadelbeltagi, Ashraf Elshahat and Mahmoud Dawood (2014) "Causes and Effects of Change Orders on Construction Projects in Kuwait", Int. Journal of Engineering Research and Applications,Vol. 4, Issue 7
  12. Bassioni, H. and Hamza, N. (2005), "Sources of Change Orders in Kuwait Building Constructio", MSc. Thesis Department of Construction and Building Engineering, Arab Academy for Science, Technology and Maritime Transport, Alexandria, Egypt
  13. Hanna, A., Camlic, R., Peterson, P., and Lee, M. (2004). "Cumulative effect of project changes for electrical and mechanical construction.", J. Constr. Eng. Manage., 130(6), 762-771.
  14. Assaf S. and Al-Hejji S. (2006), "Causes of delay in large construction projects", International Journal of Project Management, 24(4), 349-357.
  15.  Al-Momani A. (2000), "Construction delay: a quantitative analysis", International Journal of Project Management, 18(1), 51-59.
  16.  Chan D. and Kumaraswamy M. (2002), "Compressing construction durations: lessons learned from Hong Kong building projects", International Journal of Project Management, 20(1), 23-35.
  17. Jaydeep N. Desai, Jayeshkumar Pitroda, Prof. Jaydev J. Bhavsar (2015) "A Review On Change Order and Assessing Causes Affecting Change Order in Construction", Journal of International Academic Research For Multidisciplinary, Volume 2, Issue 12
  18. PMBOK (2005) "A guide to the project management body of knowledge", 5th Edition, ANSI Standard.
    Jeroen Dix (2007) "Better scope management during the initiative, design and construction phase of infrastructure projects", Master Thesis, Delft University of Technology
  19. A.H. Al-Dubaisi (2000) "Change Orders in Construction Projects In Saudi Arabia", M.Sc. Thesis, The college of graduate studies, KFUPM. Dhahran, Saudi Arabia, 2000

Downloads

Published

2015-08-25

Issue

Section

Research Articles

How to Cite

[1]
Sneha Yawalekar, B.E. Narkhede, Rakesh Raut, " Change Management in Electrical Instillation Projects, International Journal of Scientific Research in Science, Engineering and Technology(IJSRSET), Print ISSN : 2395-1990, Online ISSN : 2394-4099, Volume 1, Issue 4, pp.109-114, July-August-2015.